How do you compare two plan versions, and what does the forecast show?

By Daniel Stoffels

Short answer

Two plan versions are compared on the same timeline, with the same definitions and through a traceable reconciliation of their assumptions. The budget remains the agreed benchmark; the forecast shows the updated expectation from actual results achieved and the assessment of the remaining period.

Key points

  • Budget, forecast and scenario answer different questions and need their own version identifiers.
  • A profit bridge explains the path from the old expectation to the new one by volumes, prices, costs and timing shifts.
  • An assumptions sheet records the origin, validity and ownership of every material change.
  • AI can present and summarise changes; the people with business responsibility confirm causes and consequences.
Budget-to-forecast bridge in €k

Definition

A plan version is a version of the business plan recorded at a particular point in time, including its assumptions. A forecast is the updated expectation of future developments; a full-year projection combines completed actual periods with expectations for the remaining months.

Distinguish budget, forecast and scenario

The budget translates agreed targets and actions into figures. It serves, for example, to allocate resources and assess subsequent performance. If purchasing becomes more expensive or an order is lost, this original benchmark does not lose its historical value. Do not overwrite it with the latest expectation. Otherwise, the analysis loses what was originally agreed and why the target was missed or exceeded.

The forecast answers a different management question: Where are we likely to end up based on today's knowledge? It must therefore be allowed to show an unwelcome result. An unchanged ambitious target does not replace a realistic expectation. If management approves additional actions, show their assumed effect separately. Identify which effect is already secured and which could arise only after a decision that is still outstanding.

A scenario describes a possible combination of assumptions, such as weaker sales with longer payment terms. Merely calculating it does not make it the most likely development. Clearly identify the base expectation and alternative developments. A rolling forecast regularly extends the view ahead. A full-year projection, by contrast, ends at the financial year-end; both views can coexist if their purpose is clear.

Establish the same basis before comparing

Compare the same period and company scope. A full-year forecast is not directly comparable with a plan for the remaining months only. A newly acquired entity or changed allocation of product groups also changes the comparison basis. Show such changes separately before drawing conclusions about operational success or failure.

Check currency, unit, account mapping and metric definition. Thousands of euros and euros must not be mixed, nor may profit before and after depreciation and amortisation. If the structure changes, you need a mapping between the old and new structures. An additional adjusted comparison view can help; the originally approved version is retained and remains retrievable.

Also define the actuals cut-off date. Subsequent postings can change a new projection even though no future assumption has changed. Separate updates of past values from changes in the remaining-year plan. This makes it possible to identify whether the new expectation comes from business actually achieved, a corrected set of underlying data or a different assessment of the coming months.

Maintain the version and assumptions sheet together

A version name should distinguish purpose, planning period and preparation status. Add the status, such as in progress, for decision or approved. Retain every approved version with its inputs and calculations. A file labelled final does not reveal whether sales assumptions were changed later or whether it belongs to the presentation discussed.

For each material driver, the assumptions sheet contains the old and new value, reason for change, person with business responsibility and effective date. Drivers are the variables from which the plan is derived, such as sales volume, selling price, material consumption or payment receipt. Link the inputs to the calculation model. A free-text comment beside a manually entered profit total is difficult to recalculate later.

Distinguish an observed development from an assumed continuation. A higher purchase price may already be confirmed in orders; the assumption that it applies until year-end nevertheless remains a future assessment. Note open points and conditions. Management can then see which assumption must be reviewed in light of new information and who will obtain that information.

Reconcile two versions step by step

  1. Define the comparison

    Determine the starting version, target version, metric and period. Agree a sign convention: A positive effect increases profit, a negative one reduces it. Cost changes are therefore shown by their effect on profit. Keep the original cost movement available alongside this so that nobody reads increased expenditure as an improvement.

  2. Calculate changes individually

    Calculate volume, price and cost effects in a defined order. If volume and price change simultaneously, an interaction effect arises. Allocate it under a documented rule or show it separately. Different calculation orders must not silently be presented as different economic causes.

  3. Distinguish timing shifts

    Check whether an order is merely arriving later or is lost for the period considered. A shift within the same year can change monthly figures without changing the annual expectation. A delivery after year-end, however, affects the full-year projection. Agree the assumption with the function that has business responsibility.

  4. Confirm causes and actions

    Have sales, purchasing and operational functions confirm the changes relevant to them. Separate effects already realised from planned countermeasures. Document an action with an owner and decision point. A price increase not yet approved must not carry the same degree of certainty as an order already signed.

  5. Reconcile the bridge and component plans

    Add all effects to the starting value and compare the result with the target version. Every remaining difference stays visible until explained. Carry changed assumptions into the balance sheet and cash flow plan as well: Lower revenue may reduce receivables, while higher safety stock may simultaneously tie up additional funds.

From budget to updated profit expectation

The round amounts are freely chosen and stated in thousands of euros (€k). The example considers the annual operating profit of a business with unchanged scope and the same profit definition. The effects are calculated in a fixed order and do not overlap. All changes here concern expectations for the rest of the year; the completed period is identical in both versions. Volume, selling price and material price effects concern one item with a previous contribution of €60 per unit. Other business and fixed costs remain unchanged apart from the separate cost measure.

Starting from €300k, the changes total −€50k. The forecast is therefore €250k. The countermeasure of €20k is already approved within this calculation and included in the target version. Without this measure, the expectation would be €230k. Management can thus identify both the underlying deterioration and the contribution of the response.

Example: budget-to-forecast bridge in €k
ItemEffect on profitTraceable reason
Budget, starting value300Approved annual plan
Lower sales volume−602,000 → 1,000 units; −1,000 × €60 contribution per unit
Higher selling prices+301,000 units × €30 price increase
Higher material prices−401,000 units × €40 additional material costs
Approved cost measure+20Removal of a planned expense
Total changes−50−60 + 30 − 40 + 20
Forecast, target value250300 − 50

AI prepares, business functions explain

AI can list version differences, group assumption changes and draft an initial comment from checked calculations. Give it unambiguous version identifiers and definitions. Exact totals and bridges should be produced with fixed calculation rules. Missing assumptions remain visible as gaps; a plausible explanation is not evidence of the actual cause.

The substantive review asks for the source of every material change. A revenue decline alone does not prove a lost customer, nor does a cost increase prove inefficiency. The responsible function confirms the cause; finance secures the comparison and calculation. Only then does management assess the options for action. The approved comment must distinguish what is substantiated, assumed or still open.

Typical mistakes in version comparisons

Verification criterion: Another knowledgeable person can recalculate the starting value, every change and the target value from the recorded versions. They can also identify which assumption changed and which decision follows from it.

  • Overwriting the budget: Retain the target and current expectation separately so that the original decision remains assessable.
  • Only placing final values side by side: Explain material changes through drivers and their effects rather than merely rewording the difference.
  • Double counting countermeasures: Check whether an improvement is already included in a volume or cost assumption.
  • Allocating an unexplained residual: Investigate missing accounts, rounding or changed mappings before claiming causes.

From Daniel Stoffels’ practice

Consider planning and variances together

I have been doing budgets and forecasts since 2013. My controlling work includes cost centres, contribution margins and plan-to-actual variances that I calculate myself.

Since 2019, I have planned on an integrated basis: Gewinn- und Verlustrechnung (GuV, profit and loss account), balance sheet and cash flow. Cash flow forecasting is therefore also part of my planning work.

Frequently asked questions

May the forecast be below the approved target?

Yes. A current expectation must reflect the information available. Retain the target alongside it and show possible actions separately. Otherwise, the wish to meet the target conceals the actual need for action.

How do you handle actual figures corrected retrospectively?

Show their effect separately from new future assumptions. Identify the changed data version. This keeps it traceable whether the expectation changed because of the past or the view ahead.

Must every small change be commented on?

Agree a materiality threshold suitable for the business. Small similar effects can be grouped provided the calculation is retained. Strategically important changes may need their own explanation even at a low amount.

What happens to an action not yet approved?

Show its possible effect separately and state the prerequisite. Whether it belongs in the base expectation must be explicitly decided. The same effect must not then appear again as an additional opportunity.

Sources

Last updated:

General professional knowledge of business planning and controlling; Daniel Stoffels' planning experience

Summary by Heldensystem

Related questions

Next step

Free initial call, 30 minutes