Which phases make up an ERP migration?

By Daniel Stoffels

Short answer

An ERP migration comprises preparation, testing, training, dry runs, live migration, acceptance, intensified post-launch support (hypercare) and closure. Each phase needs a responsible person and verifiable results; capacity, data reconciliation and post-launch support are planned alongside day-to-day operations from the outset.

Key points

  • A migration transfers data and ongoing transactions to a new system or system structure. The business transition is part of it.
  • Each phase ends with evidence. A completed activity alone does not yet demonstrate a correct result.
  • Trial runs must reflect the later sequence and actual dependencies.
  • The changeover needs an unambiguous processing cut-off, a controlled data version and documented approval.
  • Cover, hypercare and orderly closure belong in the project plan and the effort calculation.
Each phase ends with evidence

Definition

An ERP migration is the planned transfer of data, configurations and associated business processes to another Enterprise Resource Planning system or a changed system structure. It combines technical transfer with functional validation, organisational transition and stabilisation of subsequent operations.

Define the migration scope before the checklist

A migration checklist becomes useful only when its subject is clear. Is accounting being migrated, the entire merchandise management system replaced or an entity moved into an existing application? Document the units, processes and datasets affected. Also record which applications will continue operating and which connections are needed. An overlooked handover point can interrupt an otherwise correct process.

Distinguish master data, open transactions, opening balances and completed history. Master data consists of basic details such as customers and items. Open transactions need further processing after the changeover, such as unpaid invoices or orders not yet delivered in full. Opening balances form the starting point for subsequent postings and movements. For completed history, a separate decision determines which information must remain accessible and how.

Every checklist item needs a result, responsibility, evidence and approval condition. ‘Transfer data’ is too vague as an entry. ‘Transfer outstanding customer items with document identifier, amount and due date and reconcile them to the approved opening balance’ is verifiable. Also name the person who decides when there is a difference. This keeps a list workable when a step does not succeed immediately.

Work through the phases in order

  1. Preparation: decide scope and rules

    Record data sources, process variants and dependencies. Establish target structures and mapping, meaning the assignment of old identifiers and accounts to new ones. Name data owners and resolve uncertainties before transfer. The evidence is an approved scope with documented mappings, open decisions and defined acceptance criteria.

  2. Testing: check data and complete transactions

    Check transfer rules first on selected cases and then across the intended scope. Compare counts, totals and individual items. Work through purchasing, sales, corrections and analyses. Each error receives a description, an assigned owner and a retest. The evidence consists of expected and actual results and confirmed corrections.

  3. Training: practise tasks with the intended permissions

    Have future users perform their own tasks themselves. Connect system operation with functional checks and the support route. Include deputies and rare but important special cases. A successfully processed practice case, including the necessary handovers, counts as evidence. An attendance list alone does not show whether the task has been mastered.

  4. Dry runs: rehearse the entire changeover

    A dry run reproduces the planned sequence without an actual operational changeover. Rehearse data provision, transfer, checks and approvals with the intended participants. Record duration, waiting times and variances. Repeat affected steps after material corrections. The evidence is a process log with reliable dependencies and clarified conditions for aborting.

  5. Live migration: execute the approved process

    Live migration is the actual transfer for the operational changeover. Use the defined starting data version and log every step. Establish how changes after data extraction are captured. Before repeating a step, check which transactions have already been processed successfully. The evidence links the data version used to the transfer result.

  6. Acceptance: confirm operational readiness

    Reconcile transferred balances and check the material business processes. Technical processing and functional correctness each require confirmation. These criteria are checked before the changeover; acceptance additionally confirms the actual result. Document restrictions and the decision on whether the intended processing activities can start.

  7. Hypercare: stabilise the new process

    Hypercare means intensified post-launch support. Bring issue reports together, prioritise blocked processes and resolve data errors separately from usage questions. Track backlogs and manual workarounds. Evidence consists of confirmed solutions, updated instructions and the handover of manageable remaining issues to named owners.

  8. Closure: hand over operations and open issues

    Confirm that regular support, responsible people and documentation are in place. Record remaining restrictions with their next steps. Compare effort and results with the original assumptions. Closure evidence includes the orderly handover and the decision on remaining issues. A final project meeting without these results does not end an outstanding responsibility.

Explicitly secure capacity alongside day-to-day operations

For each phase, identify who must know the data, make functional decisions and check results. These people also have ongoing tasks. The project plan must therefore show which routine work someone else takes over, what is simplified and which task is deliberately postponed. A general reference to support does not replace a named handover.

Backfill means cover for tasks that project participants would otherwise perform themselves. Include familiarisation, permissions and queries in the plan. Pay particular attention to bottlenecks in expertise: additional processing capacity is of little help if only one person can assess a complex account mapping. Prepare such decisions early and document their basis.

Effort after the changeover also belongs in the calculation. Cutting testing and data clarification does not yet demonstrate a saving. Monitor training needs, error handling and workarounds, and compare the entire transition with the plan. A migration can be assessed economically only when stabilisation is also taken into account.

Reconcile the migrated dataset transparently

The following calculation uses illustrative round numbers. All amounts are in thousands of euros, abbreviated €k. Customer invoices at the same reporting date in the same currency are compared. The opening balance contains 100 outstanding invoices totalling 200. The first import is missing 10 invoices totalling €20k; following investigation at document level, precisely these are added.

The correction gives 90 + 10 = 100 invoices and 180 + 20 = 200. Reconciling the count and amount makes the shortfall visible. On its own, however, it does not prove that every customer, due date and document identifier has been transferred correctly. Acceptance therefore also includes comparing individual items with the approved opening balance.

The calculation assumes there are no further changes between the data versions compared. If invoices or payments are entered after extraction, these need a separate transfer route and their own reconciliation. Otherwise, a difference could arise either from a transfer error or from different processing cut-offs.

Example: reconciliation of outstanding customer invoices

Table scrolls sideways

Check stageInvoice countAmount in €kInterpretation
Approved opening balance100200Authoritative comparison baseline
First import90180Investigate missing transactions
Targeted addition1020Only the identified missing invoices
Balance after correction10020090 + 10 invoices; amount: 180 + 20
Remaining difference from opening balance00Also check individual items and attributes

Control processing cut-offs and reruns

A cutover plan is the process plan for the actual changeover. It specifies the sequence, responsible people, required input results and approval point for each step. Define the point up to which the old system is processed and from when new transactions originate in the target system. Deliveries, payments and approvals still in progress need unambiguous treatment.

A restart after an abort must not recreate transactions already transferred. Unique identifiers and a log help establish what has been processed. If the status remains unclear, investigate before executing again. Returning to the previous state is not a single button either: once new transactions exist in the target system, it must be clear how they will be retained and incorporated into subsequent processing.

Prepare abort and return conditions before the changeover and rehearse them to an appropriate extent. Technical recovery and the functional continuation of business must fit together. A backup alone does not yet answer how new orders or payments created since then will be handled.

Common gaps in a migration checklist

Verification: a third party can see for each phase what was handed over, who checked it and what confirms the result. Data balances and open transactions can be explained across the changeover. Where this evidence is missing, the relevant checklist item remains open.

  • Ticking off activities alone: add the expected result, evidence and approval. An imported file can have incorrect functional assignments.
  • Comparing changing data versions: identify the reporting date and processing cut-off. Later movements are explained and transferred separately.
  • Closing corrections without retesting: rerun the affected case and check dependent analyses.
  • Equating the normal case with the entire migration: include open orders, part payments, credit notes and differing units of measure.
  • Planning project capacity only up to go-live: include acceptance, hypercare and handover to regular operations.
  • Handing over remaining issues without a recipient: name the decision, responsible person and next step. An open issue remains a task after the project ends.

From Daniel Stoffels’ practice

Plan for the whole migration

In projects I have seen, business cases fell apart because the team was expected to manage the migration alongside day-to-day operations and no cover was approved. Later, several external specialists joined at the same time and first had to familiarise themselves.

My conclusion is to actively support a migration from beginning to end: preparation, testing, training, dry runs, live migration, acceptance, hypercare and closure. Where that was missing in the projects I have seen, rework became more expensive than preparation.

Frequently asked questions

Can phases overlap?

Yes. Training, testing and data cleansing can run partly in parallel. Dependencies remain binding: a complete dry run needs sufficiently clarified rules and a suitable data version. The phase sequence describes the necessary results and their approvals, not a rigid calendar.

Who maintains the checklist?

Project management coordinates the overall status; the relevant functional owners confirm their results. A central list prevents differing reports of completion. Responsibility for functional correctness remains with the responsible people and is not transferred by maintaining the list.

How are open errors prioritised?

Assess the impact on the business, figures and controls, and the possibility of a controlled workaround. A blocked payment run has a different consequence from an unclear label. Record the priority and decision transparently rather than processing solely by arrival date.

Is one successful dry run enough?

That depends on the scope and changes made afterwards. A material change to data mapping or the process may require another run. The changeover actually planned, with its dependencies, must be supported by verifiable results.

When is the migration complete from a functional perspective?

When the agreed processes and balances have been accepted, regular support can take over and remaining issues have been assigned with clear responsibility. Also check analyses and the intended close sequence. A successful technical start alone does not meet these conditions.